Aware of our strong abilities in custom metal fabrication, a pollution control industry customer contacted Harmony Metal Fabrication with a challenging project. We were contracted to create a large “splitter” part, used in smokestack scrubbing. Our extensive experience in metal fabrication made us able to deliver a cost-effective solution that did not compromise on the customer’s requirements.

A wide variety of cutting and fabrication operations were applied to complete this project. Creation of the necessary steel plate, pipe, and bar parts required use of machining, rolling, drilling, welding, sand blasting, and painting processes. Additional cuts were performed through sawing, burning, and plasma cutting operations. Equipment we used included a band saw, a drill press, a welding station, and a CNC-controlled plasma cutter. The completed splitter unit measured 2’ in diameter and 3’ in height. Dimensional tolerances were successfully held to ±1/16". After an exterior painted finish was applied, air tight leak testing and a final dimensional inspection rounded out the project. This splitter device was fabricated with a fast lead time of only 3 weeks, built to high standards of quality made possible by our cutting-edge services.

Harmony continues to be an industry leader in metal fabrication services.  Contact us today to learn how your projects can take advantage of our services.

Request A Quote

Custom Fabrication of Steel Project Highlights

Product Name
Steel Splitter
Product Description
This splitter is used in smokestack scrubbing for the Pollution Control Industry.
Capabilities Applied/Processes
  • Sawing
  • Burning
  • Plasma Cutting
  • Machining
  • Rolling
  • Drilling
  • Fitting & Welding
  • Sand Blasting
  • Painting
Equipment Used to Manufacture Part
Band Saw
Drill Press
CNC Plasma Cutter
Overall Part Dimensions
Diameter: 2’
Height: 3’
Tightest Tolerances
Material Used
Steel Plate
Steel Pipe
Steel Bar
Material Finish
Sand Blast & Paint
In Process Testing/Inspection Performed
Air Tight Leak Testing
Final Inspection
Estimated Part Weight
400 lbs.
Industry for Use
Pollution Control
Turnaround Time
3 Weeks
Standards Met
3D CAD Drawing